Quarterly report for the three months to 30 September 2026 shows full ownership, growing investor interest and new infrastructure milestones at Aurora
We’re pleased to report significant commercial progress at the Aurora Energy Precinct, our 15.8 km² energy and industrial site near Port Augusta in South Australia’s Upper Spencer Gulf region, in our quarterly report for the three months ended 30 September 2026.
Full ownership secured
After quarter end we completed the acquisition of Vast Solar Aurora Pty Ltd, giving us full ownership of SiliconAurora Pty Ltd and the precinct. Dissolving the previous joint venture structure simplifies commercial negotiations and gives us a consolidated platform for engaging prospective customers, infrastructure partners and financiers.
During the quarter, Shane Masters was appointed CEO of SiliconAurora, the entity responsible for developing the precinct, to lead commercial development, partner negotiations and financing. Our Chief Technology and Operations Officer, Dr Peter Yaron, also presented at Tactic 2026 in Port Augusta on Aurora’s potential to support AI data centres and regional economic activity.
Stage One partner process draws interest
During the quarter, we launched an expressions of interest process for funding and development partners for Stage One. It comprises the approved 140 MW / 280 MWh battery energy storage system (BESS) and an initial 70 MW solar PV development, supporting a power purchase agreement for up to 70 MW of firm renewable power on the 275 kV transmission line.
National and international energy and infrastructure companies have responded, and interested parties are accessing the project data room. Indicative development capital for Stage One is A$350 million to A$550 million. We’re targeting partner selection in December 2026, financial close in early 2027 and commercial operation in 2028/29.
Aurora’s broader development strategy provides a pathway to approximately 2 GW of solar PV and 1 GW of firm renewable capacity, supporting electricity supply to the National Electricity Market and prospective behind-the-meter customers.
Data centres and heavy vehicle charging
We signed a Heads of Agreement with an Australian data centre operator for the proposed staged development of up to 1 GW of AI data centre infrastructure at Aurora. The operator has exclusivity over a 40-hectare development area while commercial arrangements, infrastructure requirements and the development pathway are negotiated.
We’re also progressing a connection to the 33 kV distribution network along Aurora’s western boundary. This could provide a faster, lower-cost pathway to initial commercial operations ahead of the larger 275 kV transmission connection, supporting early development for modular data centres and other energy-intensive users.
Heavy vehicle charging is another potential application, with a non-binding MoU signed with EV Charging Systems Pty Ltd to investigate a dedicated charging facility at the precinct.
Dr Kevin Moriarty, Executive Chairman, commented:
“Aurora has no close neighbours, the support of the Indigenous corporation and the South Australian Government through Crown Sponsorship of solar PV and BESS, and the potential to generate renewable power for hyperscale data centres that consume hundreds or thousands of megawatts, sometimes more than the communities in which they are situated.”
Transmission and solar progress
Commercial negotiations with BHP under our term sheet for access to the 275 kV transmission infrastructure continued during the quarter. The BESS Generator Performance Standards have been accepted by AEMO and ElectraNet, supporting progress toward a transmission connection agreement.
After quarter end we also placed a purchase order for Australian-designed 5B Maverick prefabricated solar systems for the initial 70 MW solar development, covering approximately 42 hectares. The compact, factory-assembled systems are designed to improve land-use efficiency and reduce on-site installation requirements. Our assessment indicates potential for more than 300 MW of solar generation within Aurora’s currently approved 200-hectare solar footprint.
Why Aurora
Aurora is located on the transmission lines that supply electricity to copper mines to the north, and those operations are expanding and will need much larger power supply for decades. Existing fibre optic cables on the east and west boundaries support a faster development process for data centres. Dr Moriarty said the precinct, fully developed with renewable and backup generation, can have a future powering mining operations in the long term.
What’s next
In the December quarter, our priorities at Aurora are progressing the Stage One funding and development partner process, responding to tenders for power purchase agreements, negotiating commercial arrangements with prospective data centre customers and advancing both the 33 kV and 275 kV connection pathways. We’ll also progress the technical, commercial and financing arrangements for the initial 70 MW solar and 140 MW BESS development.